PENGUKURAN EFEKTIVITAS MESIN PRODUKSI BUBBLE WRAP MENGGUNAKAN METODE OVERALL RESOURCE EFFECTIVENESS Studi Kasus PT GMP Sukses Makmur Indonesia

Authors

  • Kuncoro Adhi Gautama Universitas Teknologi Yogyakarta
  • Widya Setiafindari Universitas Teknologi Yogyakarta

DOI:

https://doi.org/10.58192/ocean.v1i4.590

Keywords:

Machine Effectiveness, Bubble Wrap, Overall Resource Effectiveness

Abstract

PT GMP Sukses Makmur Indonesia is a company engaged in the production of Bubble Wrap (bubbled plastic). This company produces 818,680 rolls with an average monthly production of 68,223 rolls. The problem that often arises at Pt Gmp Sukses Makmur Indonesia is the high production machine delay time with a downtime of 705.43 hours and a breakdown of 663.33 hours in one year, so the engine performance is less effective. This can lead to not achieving production targets which cause losses. The purpose of this study is to determine the effectiveness of the Bubble Wrap production machine using the Overall Resource Effectiveness (ORE) measuring tool and to find the causes of the problems that have been carried out using the ORE method on Bubble Wrap production machines during the period September 2021 – August 2022. ORE is a method that is useful in measuring the effectiveness of production time by taking into account the resources which include humans, machines, materials and methods. In the ORE method there are seven factors that are measured including readiness, availability of facility, changover efficiency, availability of material, availability of manpower, performance efficiency, dan quality rate. The results of measuring machine effectiveness using the Overall Resource Effectiveness (ORE) method for Ektruder machines were 76.41%, Crushers 99.59%, Cooling 98.99%, Mixers 99.79%, and Air Compressors 98.88%. Based on the method used, it is known that in the Bubble Wrap production process, the extruder machine does not meet the ORE standard of 85%, while the influencing factors are performance efficiency and quality rate. where the value of performance efficiency and Quality rate does not meet the standard so that it affects the high value of Overall Resource Effectiveness (ORE).

References

Hidayati, S.N. (2016). Pengaruh Pendekatan Keras dan Lunak Pemimpin Organisasi terhadap Kepuasan Kerja dan Potensi Mogok Kerja Karyawan. Jurnal Maksipreneur: Manajemen, Koperasi, dan Entrepreneurship, 5(2), 57-66. http://dx.doi.org/10.30588/SOSHUMDIK.v5i2.164.

Risdwiyanto, A. & Kurniyati, Y. (2015). Strategi Pemasaran Perguruan Tinggi Swasta di Kabupaten Sleman Yogyakarta Berbasis Rangsangan Pemasaran. Jurnal Maksipreneur: Manajemen, Koperasi, dan Entrepreneurship, 5(1), 1-23. http://dx.doi.org/10.30588/SOSHUMDIK.v5i1.142.

Bator, R. J., Bryan, A. D., & Schultz, P. W. (2011). Who Gives a Hoot?: Intercept Surveys of Litterers and Disposers. Environment and Behavior, 43(3), 295–315. https://doi.org/10.1177/0013916509356884.

Aprina, B. (2019). Analisa Overall Resource Effectiveness Untuk Meningkatkan Daya Saing dan Operational Excellance. JITMI (Jurnal Ilmiah Teknik Dan Manajemen Industri), 2.

Febriyanti, D., & Fatma, E. (2018). Analisis Efektivitas Mesin Produksi Menggunakan Pendekatan Failure and Mode Effect Analysis dan Logic Tree Analysis. JIEMS (Journal of Industrial Engineering and Management Systems), 11(1), 39–47. https://doi.org/10.30813/jiems.v11i1.1015

Maulana, F. E., Atmaji, F. T. D., & Pamoso, A. (2020). Usulan Penerapan Total Productive Maintenance (TPM) Office Menggunakan Overall Resource Equipment (ORE) Untuk Mesin Air Jet Loom (AJL). 13–18.

Puspita, L. E., & Widjajati, P. (2021). Pengukuran Efektivitas Mesin Latexing pada Produksi Karpet Permadani dengan Menggunakan Metode Overall Equipment Effectiveness (OEE) dan Overall Resource Effectiveness (ORE) di PT. XYZ. In Juminten : Jurnal Manajemen Industri dan Teknologi (Vol. 02, Issue 04).

Ramadhan, F. N., Budiasih, E., & Pamoso, A. (2021). Evaluasi Efektivitas Pemanfaatan Mesin CNC HURCO dengan Metode Overall Equipment Effectiveness (OEE) dan Overall Resource Effectiveness (ORE). 8(5).

Wardani, I. K., Tatas, F., Atmaji, D., & Alhilman, J. (2021). An Autonomous Maintenance Design Based on Overall Resource Effectiveness ( ORE ) Analysis : A Case Study of Paving Molding Machine. 6869. https://doi.org/10.23917/jiti.v20i2.15627

Downloads

Published

2022-12-28

How to Cite

Kuncoro Adhi Gautama, & Widya Setiafindari. (2022). PENGUKURAN EFEKTIVITAS MESIN PRODUKSI BUBBLE WRAP MENGGUNAKAN METODE OVERALL RESOURCE EFFECTIVENESS Studi Kasus PT GMP Sukses Makmur Indonesia. Ocean Engineering : Jurnal Ilmu Teknik Dan Teknologi Maritim, 1(4), 109–120. https://doi.org/10.58192/ocean.v1i4.590