Analisis Percepatan Proyek Pembangunan Junior Staff Camp Thiess KBU dengan Metode Crash Program Menggunakan Primavera P6
DOI:
https://doi.org/10.58192/ocean.v5i3.5460Keywords:
Crash Program, Critical path, Manpower, Primavera P6, Project AccelerationAbstract
Construction projects consist of a series of interconnected activities; consequently, delays in specific activities can impact the project's overall completion time. The Junior Staff Camp construction project at the Thiess KBU site experienced delays relative to the planned schedule, necessitating an acceleration strategy to mitigate these delays. This study aims to analyze the implementation of a "Crash Program" method—specifically by increasing the workforce for critical path activities using Primavera P6—and to evaluate the resulting changes in project duration and labor requirements. A quantitative approach was employed, utilizing actual project data such as planned and actual schedules, work progress, work volumes, activity durations, activity dependencies, and workforce data. The analysis involved identifying delays, determining the critical path, selecting activities suitable for acceleration, calculating durations following workforce increases, and rescheduling using Primavera P6. The results indicate a planned project duration of 88 days, whereas the actual duration reached 122 days, representing a 34-day delay. Five critical activities—A7030, A7130, A7190, A7210, and A7520—were selected for acceleration through the addition of four workers. Rescheduling results showed a reduction in project duration to 109 days, achieving a 13-day (10.66%) acceleration, alongside an increase in peak manpower from 27 to 31 workers. Although the Crash Program scenario successfully reduced the delay, it was unable to restore the project duration to the original planned schedule.
References
Anggara, E. R., & Namara, I. (2021). Analisis percepatan waktu menggunakan metode crashing pada pembangunan Tower 7 Proyek Apartemen Tokyo Riverside. Dalam Seminar Nasional Ketekniksipilan, Infrastruktur dan Industri Jasa Konstruksi (KIIJK).
Chairurraziqin, M., Adi, H. P., & Satrio, E. M. (2025). Evaluasi biaya dan waktu proyek menggunakan metode earned value analysis dan crashing. Jurnal Ilmiah Sultan Agung.
Faqihhuddin, M. F. (2024). Analisis biaya dan waktu dengan metode time cost trade off menggunakan aplikasi Primavera P6. Ocean Engineering: Jurnal Ilmu Teknik dan Teknologi Maritim, 3(3), 1–11.
Hidayah, A. N., Setiawan, A., & Setiono. (2024). Optimasi biaya dan waktu menggunakan metode time cost trade off. Dinamika Teknik Sipil: Majalah Ilmiah Teknik Sipil, 17(1).
Himawan, A. Y., Setiono, & Rifai, M. (2023). Analisis percepatan pada proyek pembangunan Gedung MTSN 4 Sragen dengan metode time cost trade off analysis dengan software Primavera 6.0. Matriks Teknik Sipil, 11(2).
Kerzner, H. (2022). Project management: A systems approach to planning, scheduling, and controlling (13th ed.). John Wiley & Sons.
Matahelumual, R., Jamlaay, O., & Sahusilawane, T. (2022). Analisa percepatan proyek dengan metode crashing program pada proyek pembangunan Gedung Auditorium IAIN Kota Ambon. Journal Agregate, 1(1), 65–72.
Meganda, D. F., & Witjaksana, B. (2024). Analisis percepatan proyek pembangunan menggunakan metode crashing dengan penambahan tenaga kerja dan shift kerja. Jurnal Review Pendidikan dan Pengajaran, 7(4), 17053–17059.
Muhibbin, I., Hariyadi, H., Hamdani, H., & Samengasbumi, R. P. (2024). Pemanfaatan program Primavera 6.0 sebagai efisiensi pelaksanaan pekerjaan crashing. Innovative: Journal of Social Science Research, 4(5), 1776–1790.
Nugraha, I. M. F. P., Sudiarsa, M., & Setyono, E. Y. (2023). Analisis optimasi waktu dan biaya proyek dengan penambahan sumber daya menggunakan metode time cost trade off. Dalam Prosiding Seminar Nasional Ketekniksipilan Bidang Vokasional, 2(1).
Nurazizah, N., Firdasari, & Purwandito, M. (2023). Penerapan metode time-cost trade-off dalam optimalisasi biaya dan jadwal proyek Laboratorium Dasar Universitas Samudra. Jurnal Ilmiah Telsinas Elektro, Sipil dan Teknik Informasi, 6(1), 94–103.
Oracle Corporation. (2024). Oracle Primavera P6 EPPM user guide version 24. Oracle Corporation.
Praganingrum, T. I., Pradnyadari, N. L. M. A. M., & Dwipayana, I. K. K. (2023). Analisis pengaruh percepatan waktu pelaksanaan terhadap biaya (time cost trade off) berbasis Microsoft Project. Jurnal Ilmiah Kurva Teknik, 12(1), 21–28.
Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK® guide) (7th ed.). Project Management Institute.
Regel, N., & Waskito, J. P. H. (2022). Penerapan metode crash program untuk menganalisa keterlambatan waktu penyelesaian proyek. Axial: Jurnal Rekayasa dan Manajemen Konstruksi, 10(1), 35–41.
Rivaldy, M., Oppier, I., Sangadji, F. A., & Latuconsina, S. I. (2023). Optimalisasi pelaksanaan pekerjaan dengan menggunakan metode crashing pada pembangunan rumah susun Pemerintah Kota Tual. Jurnal MESIL (Mesin Elektro Sipil), 4(1), 11–16.
Salasa, B. S., Sari, D. P., Sudibyo, A., & Nur, A. R. (2023). Optimasi waktu dan biaya pelaksanaan proyek jalan dengan metode crash program. Rekayasa Sipil, 17(1), 47–53.
Soetjipto, J. W., Adinanda, D. A., & Arifin, S. (2024). Pengendalian penyelesaian proyek berbasis kinerja menggunakan hybrid earned value–crash program. Jurnal Aplikasi Teknik Sipil, 22(2), 127–138.
Tangkeallo, N. V., Latupeirissa, J. E., & Tiyouw, H. C. P. (2024). Analisis biaya dan waktu proyek konstruksi dengan metode duration cost trade off. Paulus Civil Engineering Journal.
Usman, S., Muhammad, A. H., Adjam, I., & Altarans, I. (2023). Optimasi biaya dan waktu pelaksanaan proyek konstruksi dengan penambahan jam kerja dan tenaga kerja menggunakan metode time cost trade off. DINTEK, 16(1), 17–31.
Utari, R. P., Samin, Hadad, M. N., & Wahyudiono, S. (2022). Analisis percepatan proyek dengan metode time cost trade off. Jurnal Media Teknik Sipil, 20(1).
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Ocean Engineering : Jurnal Ilmu Teknik dan Teknologi Maritim

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.