Analisis Biaya dan Waktu dengan Metode Time Cost Trade Off menggunakan Aplikasi Primavera P6

Authors

  • Muhammad Fahri Faqihhuddin Universitas Sebelas Maret

DOI:

https://doi.org/10.58192/ocean.v3i3.2411

Keywords:

Time Cost Trade Off, Primavera P6, Crashing, Direct Costs

Abstract

In the construction industry, management costs and construction project time are important factors for achieving project success. Cost overruns and time delays can result in significant financial losses for project owners and contractors. Therefore, it is important to adopt an effective approach to construction management to optimize project costs and time. One method for overcoming problems in achieving construction project cost and time targets is the Time Cost Trade Off (TCTO) method. The TCTO method is an approach used in construction project management to achieve a balance between project costs and time. The analysis results show that the FO Krian Development Project, which has a normal duration of 522 days, can be accelerated to 500 days (scenario 1) and 498 days (scenario 2). Direct costs tend to increase due to additional working hours and additional workforce. The alternative used or which is more profitable in completing the project is to use scenario 2, namely additional labor due to a decrease in duration of 24 days from the normal project time and experiencing a decrease in total project costs of IDR 292,008,708.16.

References

Brando, R., Walangitan, P. D. R. O., & Tjakra, J. (2017). Sistem pengendalian waktu dengan critical path method (CPM) pada proyek konstruksi (Studi kasus: Menara Alfa Omega Tomohon). Jurnal Sipil Statik, 5(6), 363–371.

Elita Saragi, T., & Uli Situmorang, R. A. (2022). Optimasi waktu dan biaya percepatan proyek menggunakan metode TCTO dengan alternatif penambahan tenaga kerja dan jam kerja (lembur) (Studi kasus: Pembangunan gedung convention hall Kab. Deli Serdang). Jurnal Teknik Sipil, 1(2).

Fardila, D., & Robbyatul Adawyah, N. (2021). Optimasi biaya dan waktu proyek konstruksi dengan lembur dan penambahan tenaga kerja. INERSIA: LNformasi Dan Ekspose Hasil Riset Teknik Sipil Dan Arsitektur, 17(1), 35–46. https://doi.org/10.21831/inersia.v17i1.39499

Frederika, A. (2010). Analisis percepatan pelaksanaan dengan menambah jam kerja optimum pada proyek konstruksi (Studi kasus: Proyek pembangunan super villa, Peti Tenget-Badung). Jurnal Ilmiah Teknik Sipil, 14(2).

Ilmiah, J., & Teknika, S. (2016). Analisis percepatan waktu dan biaya proyek konstruksi dengan penambahan jam kerja (lembur) menggunakan metode time cost trade off: Studi kasus proyek pembangunan prasarana. Jurnal Ilmiah Teknik Sipil, 19(1).

Ilmiah, J., & Teknika, S. (2017). Studi optimasi waktu dan biaya dengan metode time cost trade off pada proyek konstruksi: Studi kasus proyek jalan Bugel-Galur-Poncosari Cs. Tahap I, Provinsi D.I. Yogyakarta. Jurnal Ilmiah Teknik Sipil, 20(2).

Iramutyn, V. A. (2010). Optimasi waktu dan biaya dengan metode crash time and cost optimization using crash method. [Unpublished manuscript].

Jati, A. S., Setiono, S., & Rifai, M. (2022). Analisis optimasi biaya dan waktu proyek dengan metode time cost trade off menggunakan aplikasi Primavera P6 (Studi kasus proyek gedung Teknik Universitas Jendral Soedirman). Matriks Teknik Sipil, 10(1), 53. https://doi.org/10.20961/mateksi.v10i1.55435

Kareth, M., Tarore, H., Tjakra, J., & Walangitan, D. R. O. (2012). Analisis optimalisasi waktu dan biaya dengan program Primavera 6.0 (Studi kasus: Proyek perumahan Puri Kelapa Gading). Jurnal Sipil Statik, 1(1).

Mutia Astari, N., & Momon Subagyo, A. (n.d.). Perencanaan manajemen proyek dengan metode CPM (critical path method) dan PERT (program evaluation and review technique). Jurnal Konstruksia, 13.

Putri Cahya Ardika, O., & Sri Handayani, F. (2014). Analisis TCTO dengan penambahan jam kerja pada proyek konstruksi (Studi kasus: Proyek pembangunan jalan tol Bogor Ring Road seksi II A).

Raharjo, R. W., & Musyafa, A. (2018). Prosiding kolokium program studi teknik sipil (KPSTS) FTSP UII.

Widyo Kisworo, R., & Sri Handayani, F. (2017). Analisis percepatan proyek menggunakan metode time cost trade off dengan penambahan jam kerja lembur dan jumlah alat.

Downloads

Published

2024-07-31

How to Cite

Muhammad Fahri Faqihhuddin. (2024). Analisis Biaya dan Waktu dengan Metode Time Cost Trade Off menggunakan Aplikasi Primavera P6. Ocean Engineering : Jurnal Ilmu Teknik Dan Teknologi Maritim, 3(3), 01–11. https://doi.org/10.58192/ocean.v3i3.2411