Analisis Perbandingan Produktivitas Jam Kerja Pada Proyek Reparasi Kapal TB Ampenan 01 Dengan Metode Critical Path Method dan Critical Chain Project Management di Galangan Kapal Madura
DOI:
https://doi.org/10.58192/ocean.v4i4.1353Keywords:
critical method, critical chain, galangan kapal Madura.Abstract
Project scheduling is an important element for shipyard companies to gain more profit. The most frequently used analysis is the Critical Path Method (CPM). However, in reality, planning using the CPM method is considered less efficient because it does not consider the productivity of each job in it and adds safety time which causes the project duration to become longer. In accordance with the above problems, a new method for planning project schedules is now being developed, namely Critical Chain Project Management (CCPM). CCPM is a project planning method that emphasizes the resources needed to carry out existing tasks in the project. This method is carried out by eliminating multitasking, student syndrome, Parkinson's law and providing a buffer at the end of the project. In this final project, a comparison of the duration of the results of applying the CCPM method with the Critical Path Method (CPM) method is carried out in a case study of ship repairs at PT. Galangan Kapal Madura. The initial project scheduling uses the traditional method in the form of a Gantt chart which is then broken down in more detail and completely with the relationship between activities in the form of CPM, and then will be compared with the duration of the results of CCPM scheduling which has eliminated multitasking, eliminated Safety time for each activity and provided a buffer in the work.
References
Astari, N. M., Subagyo, A. M., & Kusnadi, K. (2024). Perencanaan manajemen proyek dengan metode CPM dan PERT pada pembangunan Museum XYZ. Konstruksia, 13(1), 164–180. https://doi.org/10.24853/jk.13.1.164-180
Fadila, N., Suliawati, S., & Arfah, M. (2024). Analisis manajemen proyek dengan metode CPM pada pembangunan rumah subsidi. Factory: Jurnal Industri, Manajemen dan Rekayasa Sistem Industri, 3(1), 9–19. https://doi.org/10.56211/factory.v3i1.616
Fausan, A., Jusmidah, J., Sulistiono, W., & Nurhidayah, N. (2025). Evaluasi manajemen waktu dan biaya proyek menggunakan Critical Path Method. Jurnal Ilmiah Ecosystem, 25(3), 7999. https://doi.org/10.35965/eco.v25i3.7999
Sinurat, F., & Misdalena, F. (2024). Analisis manajemen proyek dengan metode CPM pada proyek pembangunan Gedung Chandra Tanjung Karang. Jurnal Konstruksi, 22(2), 98–107. https://doi.org/10.33364/konstruksi/v.22-2.2131
Fijra, R., Rahmalia Putri, A., Mawasandi, F., & Harisnanda, F. (2025). Implementasi Critical Path Method pada proyek perumahan XYZ untuk meningkatkan efisiensi manajemen proyek. Journal Industrial Engineering and Management (JUST-ME), 6(01), 86–93. https://doi.org/10.47398/justme.v6i01.105
Rolangon, A. A., Dundu, A. K. T., & Malingkas, G. Y. (2024). Penerapan metode CPM dalam perencanaan manajemen proyek jalan Molompar Utara-Wawali Pasan. TEKNO. https://doi.org/10.35793/jts.v22i90.58785
Wilar, W. P. R., Malingkas, G. Y., & Mangare, J. B. (2025). Penerapan manajemen waktu dengan metode CPM pada proyek pembangunan laboratorium SMKS Kema Perintis. TEKNO, 23(91), 60792. https://doi.org/10.35793/jts.v23i91.60792
Gultom, P., Simamora, E., Nehe, J. A., Tambunan, C. H., Purba, D. B., & Tamba, A. O. (2025). Penerapan metode jalur kritis dalam perencanaan proyek. Ekopedia: Jurnal Ilmiah Ekonomi, 421. https://doi.org/10.63822/bdd4r493
Wulan, T. W., Jusmidah, J., & Haerianti, H. (2025). Evaluasi manajemen waktu menggunakan metode CPM pada proyek pembangunan ruang Puskesmas Lamasi, Kabupaten Luwu. Jurnal Ilmiah Ecosystem, 25(3), 7965. https://doi.org/10.35965/eco.v25i3.7965
Nukuhehe, S., Saleh, L. M., & Gaspersz, W. (2025). Analisis penjadwalan proyek konstruksi dengan Critical Path Method pada pembangunan Poliklinik Fakultas Kedokteran Universitas Pattimura Ambon. Jurnal Penelitian Multidisiplin Bangsa, 1(8), 184. https://doi.org/10.59837/jpnmb.v1i8.184
Sandora, R., & Tridya, D. R. (2025). Implementation of Critical Chain Project Management method on controlling the pipeline project. Tibuana: Journal of Applied Industrial Engineering, 8(1), 15–21. https://doi.org/10.36456/tibuana.8.1.9988.15-21
Aulady, M. F. N., & Orleans, C. (2016). Analysis of the Critical Chain Project Management (CCPM) method, BIM 3D, and Last Planner System on contractor performance. Eduvest-Journal of Universal Studies, 5(3), 2716–2730. https://doi.org/10.59188/eduvest.v5i3.1754
(n.d.). Implementation of the Critical Chain Project Management (CCPM) model for improving time and cost in a project for house type 36. ResearchGate. (2025).
(n.d.). Critical chain project management: under investigation or case closed? Paper presented at PMI Research and Education Conference. Grant, K. P., & Gergely, M. (2012). Project Management Institute.
(n.d.). A review of Critical Chain Project Management (CCPM). Research Article. (2018). Tarbiat Modares University.
Downloads
Published
Versions
- 2026-01-29 (2)
- 2025-12-29 (1)
How to Cite
Issue
Section
License
Copyright (c) 2026 Ocean Engineering : Jurnal Ilmu Teknik dan Teknologi Maritim

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.